New construction
Installation of a prefab pit in a new construction situation usually takes place before the roof is on the building. This makes the installation easier.
Existing workshop
Installation of a prefab pit in an existing situation is not much different than at a newbuild workshop. The main difference is that sawing must be done in the workshop floor and that the placement of the pit will be done through a door and with a roof on the building. The pit is often partially lifted inward, after which the pit is rolled into place.
Dig a hole
Saw in workshop floor and dig a hole
Laying the foundation for the pit
Laying the foundation for the pit
Install and level the pit
Install and level the pit
Poor concrete up to 20 cm and rest with stabilised sand
Poor concrete up to 20 cm and rest with stabilised sand
Apply PVC pipes to transits
Apply PVC pipes to transits
Apply reinforcement to pit, pour floor and finish
Apply reinforcement to pit, pour floor and finish